School Renewal Investment Report

2025-2026 Projects Planned & Underway
SCHOOL NAME PROJECT DESCRIPTION CONSTRUCTION START DATE COMPLETED DATE or ANTICIPATED COMPLETION DATE PERCENT COMPLETE %
A K Wigg PS Accessibility Upgrade 2025-09-01 2026-08-31 10%
A K Wigg PS Roof Replacement 2025-09-01 2026-08-31  
A N Myer SS Roof Replacement 2025-09-01 2026-08-31  
Applewood PS Roof Replacement 2025-09-01 2026-08-31  
Applewood PS Security Upgrade 2024-09-01 2026-03-31 65%
Briardale PS Accessibility Upgrade 2025-09-01 2026-08-31 10%
Briardale PS Multi System Upgrade 2025-09-01 2026-08-31 25%
Briardale PS Security Upgrade 2024-09-01 2026-03-31 10%
Bridgeview PS Roof Replacement 2025-09-01 2026-08-31  
Bridgeview PS Security Upgrade 2024-09-01 2026-03-31 65%
Burleigh Hill PS Security Upgrade 2025-09-01 2026-08-31 10%
Caistor Central PS Security Upgrade 2025-09-01 2026-08-31 10%
Central-Livingston Roof Replacement 2025-09-01 2026-08-31  
Central-Livingston Security Upgrade 2025-09-01 2026-08-31 10%
Cherrywood Acres PS Accessibility Upgrade 2025-09-01 2026-08-31 10%
Cherrywood Acres PS Floor Finishes 2025-09-01 2026-03-31 100%
Connaught PS HVAC System Upgrade 2023-09-01 2026-03-31 75%
Crossroads PS Security Upgrade 2025-09-01 2026-08-31 10%
Dewitt Carter PS Exterior Walls 2025-09-01 2026-08-31 10%
Dewitt Carter PS Roof Replacement 2025-09-01 2026-08-31  
DSBN Academy HVAC System Upgrade 2025-09-01 2026-08-31 10%
E I McCulley PS HVAC System Upgrade 2025-09-01 2026-08-31  
E L Crossley SS HVAC System Upgrade 2022-09-01 2026-03-31 95%
E L Crossley SS Interior Renovations 2025-09-01 2026-08-31 10%
E L Crossley SS Plumbing Upgrade 2025-09-01 2026-08-31 10%
E L Crossley SS Roof Replacement 2025-09-01 2026-08-31  
Eastdale SS Accessibility Upgrade 2025-09-01 2026-08-31 50%
Eastdale SS Multi System Upgrade 2023-09-01 2028-08-31 50%
Eastdale SS Roof Replacement 2025-09-01 2026-08-31 10%
Eden HS Accessibility Upgrade 2025-09-01 2026-08-31 10%
Eden HS Sports Field Upgrade 2022-09-01 2026-08-31 85%
Edith Cavell PS HVAC System Upgrade 2024-09-01 2026-03-31 100%
Ferndale PS Floor Finishes 2025-09-01 2026-08-31  
Ferndale PS Security Upgrade 2024-09-01 2026-03-31 65%
Fitch Street PS Multi System Upgrade 2024-09-01 2026-08-31 95%
Fitch Street PS Paving & Resurfacing 2025-09-01 2026-08-31  
Forestview PS Security Upgrade 2025-09-01 2026-08-31 10%
Gainsborough Central PS Multi System Upgrade 2023-09-01 2026-03-31 100%
Gainsborough Central PS Security Upgrade 2025-09-01 2026-08-31 10%
Garrison Road PS Floor Finishes 2025-09-01 2026-08-31  
Glendale PS Accessibility Upgrade 2025-09-01 2026-08-31 10%
Glendale PS Roof Replacement 2025-09-01 2026-08-31 10%
Glynn A Green PS Security Upgrade 2025-09-01 2026-08-31 10%
Gordon PS Security Upgrade 2024-09-01 2026-03-31 65%
Governor Simcoe SS Accessibility Upgrade 2025-09-01 2026-08-31 10%
Governor Simcoe SS Lighting Upgrade 2024-09-01 2026-08-31 80%
Gracefield PS Electrical Upgrade 2024-09-01 2026-08-31 25%
Grand Avenue PS Security Upgrade 2025-09-01 2026-08-31 10%
Grapeview PS Accessibility Upgrade 2023-09-01 2026-08-31 60%
Grapeview PS Electrical Upgrade 2023-09-01 2026-08-31 60%
Grapeview PS HVAC System Upgrade 2023-09-01 2026-08-31 60%
Grapeview PS Security Upgrade 2024-09-01 2026-03-31 65%
Greendale PS Security Upgrade 2025-09-01 2026-08-31 10%
Harriet Tubman PS Security Upgrade 2025-09-01 2026-08-31 10%
Heximer Avenue PS Accessibility Upgrade 2025-09-01 2026-08-31 10%
James Morden PS HVAC System Upgrade 2025-09-01 2026-08-31 20%
James Morden PS Roof Replacement 2025-09-01 2026-08-31  
James Morden PS Site Improvements 2024-09-01 2026-03-31 10%
Jeanne Sauve PS Security Upgrade 2024-09-01 2026-03-31 65%
John Brant PS Security Upgrade 2025-09-01 2026-08-31 10%
John Marshall PS Roof Replacement 2025-09-01 2026-08-31  
John Marshall PS Security Upgrade 2025-09-01 2026-08-31 10%
Kate S Durdan PS Security Upgrade 2025-09-01 2026-08-31 10%
Lakeview PS Security Upgrade 2025-09-01 2026-08-31 10%
Laura Secord SS Lighting Upgrade 2023-09-01 2026-08-31 10%
Lifetime Learning Centre Window Replacement 2025-09-01 2026-03-31 100%
Martha Cullimore PS Lighting Upgrade 2025-09-01 2026-08-31 10%
Martha Cullimore PS HVAC System Upgrade 2025-09-01 2026-08-31 10%
McKay PS Security Upgrade 2025-09-01 2026-08-31 10%
Nelles PS Security Upgrade 2025-09-01 2026-08-31 10%
Oakridge PS HVAC System Upgrade 2025-09-01 2026-08-31 10%
Oakridge PS Security Upgrade 2025-09-01 2026-08-31 10%
Ontario PS Electrical Upgrade 2024-09-01 2026-08-31 25%
Parnall PS Floor Finishes 2025-09-01 2026-03-31 100%
Parnall PS HVAC System Upgrade 2024-09-01 2026-03-31 100%
Peace Bridge PS Roof Replacement 2025-09-01 2026-08-31  
Pine Grove PS Paving & Resurfacing 2025-09-01 2026-08-31  
Plymouth PS Security Upgrade 2025-09-01 2026-08-31 10%
Port Colborne HS Multi System Upgrade 2025-09-01 2030-08-31  
Power Glen PS Floor Finishes 2025-09-01 2026-03-31 100%
Prince of Wales PS (St Cath) HVAC System Upgrade 2025-09-01 2026-03-31 100%
Prince of Wales PS (St Cath) Security Upgrade 2025-09-01 2026-08-31 10%
Prince of Wales PS (St Cath) Wall Finishes 2025-09-01 2026-03-31 100%
Prince Philip PS (NF) Security Upgrade 2025-09-01 2026-08-31 10%
Prince Philip PS (St Cath) Security Upgrade 2025-09-01 2026-08-31 10%
Princess Elizabeth PS Floor Finishes 2023-09-01 2026-03-31 100%
Princess Elizabeth PS Interior Renovations 2023-09-01 2026-03-31 100%
Princess Elizabeth PS Lighting Upgrade 2023-09-01 2026-03-31 100%
Princess Elizabeth PS Site Improvements 2025-09-01 2026-03-31 100%
Princess Elizabeth PS Window Replacement 2023-09-01 2026-03-31 100%
Princess Margaret PS Accessibility Upgrade 2025-09-01 2026-08-31 10%
Princess Margaret PS Floor Finishes 2025-09-01 2026-03-31 100%
Princess Margaret PS Exterior Walls 2025-09-01 2026-03-31 100%
Quaker Road PS Multi System Upgrade 2024-09-01 2026-03-31 100%
Quaker Road PS Wall Finishes 2025-09-01 2026-03-31 100%
Richmond Street PS Security Upgrade 2025-09-01 2026-08-31 10%
River View PS HVAC System Upgrade 2024-09-01 2026-08-31 95%
River View PS Roof Replacement 2024-09-01 2026-08-31 95%
River View PS Security Upgrade 2024-09-01 2026-03-31 65%
Ross PS Security Upgrade 2025-09-01 2026-08-31 10%
Simcoe Street PS Wall Finishes 2025-09-01 2026-08-31  
Sir Winston Churchill SS Floor Finishes 2025-09-01 2026-03-31 100%
Sir Winston Churchill SS Roof Replacement 2025-07-01 2026-03-31 100%
Smith PS Security Upgrade 2025-09-01 2026-08-31 10%
Smithville PS Electrical Upgrade 2024-09-01 2026-08-31 25%
Smithville PS Security Upgrade 2025-09-01 2026-08-31 10%
St Catharines Collegiate SS Roof Replacement 2025-09-01 2026-08-31  
St Davids PS Electrical Upgrade 2025-09-01 2026-08-31 10%
Stamford Collegiate SS Floor Finishes 2025-09-01 2026-08-31  
Stamford Collegiate SS Site Improvements 2025-09-01 2026-03-31 100%
Stamford Collegiate SS Roof Replacement 2025-09-01 2026-08-31 10%
Steele Street PS Accessibility Upgrade 2023-09-01 2026-03-31 100%
Steele Street PS Electrical Upgrade 2023-09-01 2026-03-31 100%
Steele Street PS Floor Finishes 2023-09-01 2026-03-31 100%
Steele Street PS HVAC System Upgrade 2023-09-01 2026-03-31 100%
Steele Street PS Roof Replacement 2023-09-01 2026-03-31 100%
Steele Street PS Security Upgrade 2024-09-01 2026-03-31 65%
Stevensville PS Floor Finishes 2025-09-01 2026-03-31 100%
Stevensville PS Security Upgrade 2024-09-01 2026-03-31 65%
Thorold SS Accessibility Upgrade 2025-09-01 2026-08-31 10%
Thorold SS Multi System Upgrade 2023-09-01 2028-08-31 25%
Twenty Valley PS Security Upgrade 2025-09-01 2026-08-31 10%
Valley Way PS Paving & Resurfacing 2025-09-01 2026-08-31  
Valley Way PS Security Upgrade 2025-09-01 2026-08-31 10%
Victoria PS Exterior Walls 2025-09-01 2026-08-31  
Victoria PS Roof Replacement 2025-09-01 2026-08-31  
Welland Centennial SS Accessibility Upgrade 2025-09-01 2026-08-31 40%
Welland Centennial SS Multi System Upgrade 2023-09-01 2027-08-31 40%
Welland Centennial SS Roof Replacement 2025-09-01 2026-08-31 10%
Wellington Heights PS Security Upgrade 2025-09-01 2026-08-31 10%
Westlane SS Interior Renovations 2025-09-01 2026-08-31  
Westlane SS Roof Replacement 2025-07-01 2026-03-31 100%
Westlane SS Roof Replacement 2025-09-01 2026-08-31 10%
Westmount PS Security Upgrade 2025-09-01 2026-08-31 10%
William H Merritt PS Security Upgrade 2025-09-01 2026-08-31 10%
2024-2025 Completed Projects
SCHOOL NAME PROJECT DESCRIPTION CONSTRUCTION START DATE COMPLETED DATE or ANTICIPATED COMPLETION DATE PERCENT COMPLETE %
A K Wigg PS HVAC System Upgrade 2024-09-01 2025-03-31 100%
A N Myer SS Security Upgrade 2022-09-01 2025-08-31 100%
Applewood PS HVAC System Upgrade 2023-09-01 2025-08-31 100%
Applewood PS HVAC System Upgrade 2024-09-01 2025-08-31 100%
Applewood PS Lighting Upgrade 2023-09-01 2025-08-31 100%
Applewood PS Paving & Resurfacing 2025-07-01 2025-08-31 100%
Bridgeview PS Accessibility Upgrade 2025-09-01 2025-08-31 100%
Bridgeview PS Multi System Upgrade 2023-09-01 2025-08-31 100%
Burleigh Hill PS Accessibility Upgrade 2023-09-01 2025-08-31 100%
Burleigh Hill PS Floor Finishes 2023-09-01 2025-08-31 100%
Burleigh Hill PS HVAC System Upgrade 2023-09-01 2025-08-31 100%
Burleigh Hill PS Plumbing Upgrade 2023-09-01 2025-08-31 100%
Caistor Central PS Roof Replacement 2025-07-01 2025-08-31 100%
Central PS Electrical Upgrade 2024-09-01 2025-08-31 100%
Central PS Electrical Upgrade 2024-09-01 2025-03-31 100%
Central PS Security Upgrade 2024-09-01 2025-03-31 100%
Cherrywood Acres PS Interior Renovations 2024-09-01 2025-03-31 100%
Cherrywood Acres PS Interior Renovations 2024-09-01 2025-08-31 100%
Cherrywood Acres PS Lighting Upgrade 2024-09-01 2025-03-31 100%
Connaught PS HVAC System Upgrade 2024-09-01 2025-03-31 100%
Connaught PS Lighting Upgrade 2024-09-01 2025-08-31 100%
Connaught PS Roof Replacement 2023-09-01 2024-12-31 100%
Connaught PS Wall Finishes 2023-09-01 2025-08-31 100%
Dalewood PS Floor Finishes 2024-09-01 2025-08-31 100%
Dalewood PS Roof Replacement 2023-09-01 2024-12-31 100%
Dewitt Carter PS HVAC System Upgrade 2022-09-01 2025-03-31 100%
DSBN Academy Electrical Upgrade 2024-09-01 2025-03-31 100%
DSBN Academy Lighting Upgrade 2023-09-01 2025-08-31 100%
DSBN Academy Security Upgrade 2022-09-01 2025-08-31 100%
E I McCulley PS Lighting Upgrade 2023-09-01 2025-03-31 100%
E I McCulley PS Roof Replacement 2025-07-01 2025-08-31 100%
E L Crossley SS Floor Finishes 2022-09-01 2025-08-31 100%
E L Crossley SS Interior Renovations 2022-09-01 2025-08-31 100%
E L Crossley SS Security Upgrade 2022-09-01 2025-08-31 100%
E L Crossley SS Wall Finishes 2022-09-01 2025-08-31 100%
E L Crossley SS Window Replacement 2022-09-01 2025-08-31 100%
Eastdale SS Security Upgrade 2022-09-01 2025-08-31 100%
Eastdale SS Sports Field Upgrade 2022-09-01 2025-08-31 100%
Eden HS Security Upgrade 2022-09-01 2025-08-31 100%
Eden HS Wall Finishes 2024-09-01 2025-08-31 100%
Edith Cavell PS Roof Replacement 2025-07-01 2025-08-31 100%
Edith Cavell PS Wall Finishes 2024-09-01 2025-03-31 100%
Ferndale PS Electrical Upgrade 2024-09-01 2025-03-31 100%
Gainsborough Central PS Accessibility Upgrade 2024-09-01 2025-08-31 100%
Garrison Road PS Roof Replacement 2025-07-01 2025-08-31 100%
Glynn A Green PS HVAC System Upgrade 2024-09-01 2025-03-31 100%
Gordon PS Roof Replacement 2023-09-01 2024-12-31 100%
Governor Simcoe SS Roof Replacement 2024-09-01 2025-08-31 100%
Governor Simcoe SS Security Upgrade 2022-09-01 2025-08-31 100%
Grand Avenue PS Electrical Upgrade 2023-09-01 2025-03-31 100%
Grand Avenue PS Electrical Upgrade 2024-09-01 2025-03-31 100%
Greater Fort Erie SS Security Upgrade 2022-09-01 2025-08-31 100%
Greendale PS Roof Replacement 2023-09-01 2024-12-31 100%
Jacob Beam PS Electrical Upgrade 2024-09-01 2025-03-31 100%
Jacob Beam PS Site Improvements 2024-09-01 2025-08-31 100%
Jeanne Sauve PS Lighting Upgrade 2023-09-01 2025-03-31 100%
Jeanne Sauve PS Wall Finishes 2024-09-01 2025-08-31 100%
John Brant PS Floor Finishes 2024-09-01 2025-03-31 100%
Kate S Durdan PS Site Improvements 2024-09-01 2025-08-31 100%
Kate S Durdan PS Roof Replacement 2023-09-01 2024-12-31 100%
Lakeview PS Electrical Upgrade 2022-09-01 2025-08-31 100%
Lakeview PS Paving & Resurfacing 2022-09-01 2025-08-31 100%
Lakeview PS Plumbing Upgrade 2022-09-01 2025-08-31 100%
Laura Secord SS Electrical Upgrade 2022-09-01 2025-03-31 100%
Laura Secord SS HVAC System Upgrade 2024-09-01 2025-03-31 100%
Laura Secord SS Security Upgrade 2022-09-01 2025-08-31 100%
Lifetime Learning Centre Electrical Upgrade 2024-09-01 2025-03-31 100%
Lockview PS HVAC System Upgrade 2022-09-01 2025-03-31 100%
Lockview PS Paving & Resurfacing 2025-09-01 2025-08-31 100%
McKay PS Accessibility Upgrade 2022-09-01 2025-08-31 100%
McKay PS Electrical Upgrade 2024-09-01 2025-03-31 100%
McKay PS Interior Doors 2024-09-01 2025-03-31 100%
Nelles PS HVAC System Upgrade 2024-09-01 2025-08-31 100%
Nelles PS Plumbing Upgrade 2024-09-01 2025-03-31 100%
Oakridge PS Wall Finishes 2024-09-01 2025-08-31 100%
Oakwood PS HVAC System Upgrade 2023-09-01 2025-03-31 100%
Oakwood PS Interior Renovations 2024-09-01 2025-08-31 100%
Oakwood PS Roof Replacement 2025-07-01 2025-08-31 100%
Ontario PS Wall Finishes 2024-09-01 2025-08-31 100%
Ontario PS Interior Renovations 2024-09-01 2025-08-31 100%
Parnall PS Floor Finishes 2024-09-01 2025-03-31 100%
Peace Bridge PS Fences & Gate Replacement 2025-07-01 2025-08-31 100%
Pine Grove PS Roof Replacement 2025-07-01 2025-08-31 100%
Plymouth PS Wall Finishes 2024-09-01 2025-08-31 100%
Port Colborne HS Security Upgrade 2022-09-01 2025-08-31 100%
Port Weller PS Lighting Upgrade 2023-09-01 2025-03-31 100%
Power Glen PS HVAC System Upgrade 2024-09-01 2025-03-31 100%
Power Glen PS Interior Doors 2024-09-01 2025-03-31 100%
Power Glen PS Roof Replacement 2025-07-01 2025-08-31 100%
Power Glen PS Wall Finishes 2024-09-01 2025-08-31 100%
Prince of Wales PS (St Cath) Exterior Doors 2024-09-01 2025-03-31 100%
Prince of Wales PS (St Cath) Roof Replacement 2025-07-01 2025-08-31 100%
Prince of Wales PS (Thorold) Accessibility Upgrade 2022-09-01 2025-08-31 100%
Prince of Wales PS (Thorold) Multi System Upgrade 2023-09-01 2025-08-31 100%
Prince Philip PS (NF) Floor Finishes 2024-09-01 2025-03-31 100%
Prince Philip PS (St Cath) HVAC System Upgrade 2022-09-01 2025-03-31 100%
Prince Philip PS (St Cath) Interior Renovations 2023-09-01 2025-08-31 100%
Princess Elizabeth PS Electrical Upgrade 2024-09-01 2025-03-31 100%
Prinecess Margaret PS Interior Renovations 2024-09-01 2025-08-31 100%
Quaker Road PS Electrical Upgrade 2024-09-01 2025-03-31 100%
River View PS Wall Finishes 2024-09-01 2025-08-31 100%
Ross PS Wall Finishes 2024-09-01 2025-03-31 100%
Senator Gibson PS Floor Finishes 2024-09-01 2025-08-31 100%
Senator Gibson PS Plumbing Upgrade 2024-09-01 2025-03-31 100%
Senator Gibson PS Roof Replacement 2023-09-01 2024-12-31 100%
Simcoe Street PS Accessibility Upgrade 2023-09-01 2025-08-31 100%
Simcoe Street PS HVAC System Upgrade 2023-09-01 2025-08-31 100%
Simcoe Street PS Plumbing Upgrade 2024-09-01 2025-03-31 100%
Sir Winston Churchill SS Interior Doors 2024-09-01 2025-08-31 100%
Sir Winston Churchill SS Interior Renovations 2024-09-01 2025-08-31 100%
Sir Winston Churchill SS Security Upgrade 2022-09-01 2025-08-31 100%
St Davids PS Interior Renovations 2024-09-01 2025-08-31 100%
St Catharines Collegiate SS Exterior Doors 2024-09-01 2025-03-31 100%
St Catharines Collegiate SS Floor Finishes 2024-09-01 2025-03-31 100%
St Catharines Collegiate SS Lighting Upgrade 2023-09-01 2025-08-31 100%
St Catharines Collegiate SS Security Upgrade 2022-09-01 2025-08-31 100%
St Catharines Collegiate SS Wall Finishes 2024-09-01 2025-08-31 100%
St Davids PS Roof Replacement 2025-07-01 2025-08-31 100%
Stamford Collegiate SS Security Upgrade 2022-09-01 2025-08-31 100%
Steele Street PS Interior Doors 2024-09-01 2025-08-31 100%
Stevensville PS Paving & Resurfacing 2025-07-01 2025-08-31 100%
Stevensville PS Wall Finishes 2024-09-01 2025-08-31 100%
Thorold SS Security Upgrade 2022-09-01 2025-08-31 100%
Twenty Valley PS Floor Finishes 2024-09-01 2025-03-31 100%
Victoria PS Accessibility Upgrade 2024-09-01 2025-08-31 100%
Victoria PS Paving & Resurfacing 2025-07-01 2025-08-31 100%
Welland Centennial SS Interior Renovations 2024-09-01 2025-03-31 100%
Welland Centennial SS Security Upgrade 2022-09-01 2025-08-31 100%
Wellington Heights PS Roof Replacement 2023-09-01 2024-12-31 100%
Westdale PS Site Improvements 2024-09-01 2025-08-31 100%
Westlane SS HVAC System Upgrade 2022-09-01 2025-08-31 100%
Westlane SS Interior Renovations 2022-09-01 2025-08-31 100%
Westlane SS Security Upgrade 2022-09-01 2025-08-31 100%
Westmount PS Fences & Gate Replacement 2024-09-01 2025-08-31 100%
Westmount PS Floor Finishes 2023-09-01 2025-03-31 100%
Woodland PS HVAC System Upgrade 2023-09-01 2025-08-31 100%
Woodland PS Lighting Upgrade 2023-09-01 2025-08-31 100%